Waterfall Creek Enhancement Project 2000
A restoration/rehabilitation plan was developed that recommended and initiated measures to address community concerns by supplying survey and design for rehabilitation work,... -
Kumealon Creek Instream Construction
Two instream rehabilitation projects were implemented in Kumealon Creek, located 56 km south of Prince Rupert. The site is only accessible by boat or air. The creek has high... -
Scully Creek Restoration Project 2013
This report discusses the Scully Creek Restoration Project, which involved improving access to quality spawning habitat by the removal of beaver dams and improved beaver... -
Kitwanga Sockeye Salmon Spawning Habitat Improvement Initiative
Since 1999, the Gitanyow Fisheries Authority has been intensively studying the Kitwanga Watershed in an effort to understand the decline of the Kitwanga sockeye stock.... -
Skeena Sockeye Lakes Hydroacoustic Surveys
Skeena Fisheries Commission (SFC) conducted hydroacoustic surveys at five sockeye rearing lakes in the Skeena Watershed. The main objectives of these surveys is to enumerate and... -
Habitat Improvement and Outplanting Possibilities - Upper Bulkley/ Morice Systems
The NCD Habitat Unit, along with coho biologists from the Science Branch, conducted a juvenile coho sampling program on the Upper Bulkley/Morice River systems during the month... -
Water Quality Effectiveness Evaluations and Fish Passage Culvert Inspection
Water Quality Effectiveness Evaluations arose out of the Forest and Range Practices Act as a way of measuring the effectiveness of the Act in accomplishing its forest... -
Wet'suwet'en Submission to the Canadian Environmental Assessment Agency -...
This submission from the Office of the Wet'suwet'en (OW) to the Canadian Environmental Assessment Agency (CEAA) is a response to the CEAA report regarding the proposed Pacific... -
Wet'suwet'en Rights and Title and Enbridge's Northern Gateway Pipelines Project
The Office of the Wet'suwet'en (OW) presents this submission to the Northern Gateway Joint Review Panel. This submission is a component of the Wet'suwet'en response in respect... -
Upper Skeena and Kispiox River Juvenile Steelhead Surveys 1999
In 1999, the Ministry of Environment, Lands, and Parks surveyed portions of the Upper Skeena River and Kispiox Rivers during September 1999 for juvenile steelhead and fry and... -
Upper Bulkley River Steelhead Population Monitoring
The upper Bulkley River system, near Houston, was first assessed by the Fish Habitat Improvement Section in 1981. The initial assessment identified probably areas of importance... -
Telkwa Coal Project: Application for a Project Approval Certificate
The Application should be read in the context that it is the basis for the first major stage of the Environmental Assessment Process as it applies to new mine developments... -
Telkwa Coal Project Appendix 12: Aquatic Resource Assessment 1985
Studies were undertaken during 1984 to evaluate aquatic resources in the Telkwa Project study area in west-central British Columbia. Stream periphyton, invertebrates, and fish... -
Stream Inventory: Fenton Creek and Adjacent Tributaries 1997
This survey provides an assessment of fish presence/absence in Fenton Creek and its adjacent tributaries. It identifies stream gradients and reasons for obstructed fish passage,... -
Some Notes on the Habits and Habitat of Steelhead Trout in the Kispiox River...
During the spring and summer of 1976, two investigations funded through the salmonid enhancement program were conducted on the steelhead trout of the Kispiox River. The first... -
Research Document 2010/053: State of Fishery Resources of Pacific Marine Ecosystems
This eleventh report of an annual series updates the state of physical, biological, and selected fishery resources of Canadian Pacific marine ecosystems. -
Research Document 2001/098: Factors Limiting Juvenile Sockeye Production
This report presents summaries of data collected from 60 B.C sockeye nursery lakes between 1977 and 2000. Factors which constrain sockeye production in each lake and, where... -
Reconnaissance (1:20,000) Fish and Fish Habitat Stream Inventory Re-Sampling...
The main objectives of the 1:20,000 fish and fish habitat reconnaissance level stream inventory project in lower Buck Creek watershed were: to review and summarize historical... -
Reconnaissance (1:20,000) Fish and Fish Habitat Inventory in the Upper Buck...
This inventory provides information regarding the characteristics, distributions, and relative abundance of fish species, as well as information on biophysical lake and stream... -
Morrison Copper/Gold Project Assessment Report
This Assessment Report considers the proposed Morrison Copper/Gold Mine Project’s potential to cause significant adverse environmental, economic, social, heritage, and health...